Jennens Court

Birmingham

Birmingham

Jennens Court

Background: After the client evaluated its property and highlighted several potential issues at Jennens Court, TSL was called to conduct further investigation on the external façade, we worked with the client and their design team to investigate and further develop a design proposal to accommodate this requirement.

Scope Of Service: Investigations, Design, Consultation, External Facade, Substrate Remedials, Spandral Panel Remedials, Coping Replacement.

Form Of Contract: JCT D&B

We were invited to participate in this project at a very early preconstruction stage, this enabled us to work closely with the client’s design team to ensure the developing proposal suited the client’s requirements as well as met all standard compliance criteria.

TSL’s industry known ability to work with minimal disruption was heavily leaned on throughout construction. We liaised extensively with the client about logistics and work sequencing due to the busy student accommodation block remaining live and discussed at length how we can minimise the impact on residents. This was mostly achieved by operating on reduced working hours throughout the project and communicating in advance with all parties.

In the early phases of the project, it was discovered that the existing building substrate and detailing were beyond standard building tolerances and quality, this resulted in additional remedial actions not only to bring the substrate up to a suitable standard for fixing but also a suitable standard for fire protection. The existing fire strategy regarding the M&E was also revised due to the now non-compliant materials present in the existing build. These solutions were worked on alongside the client’s design team to ensure the functionality was not impeded and compliance was met. Our final proposals consisted of a majority of A1 fire rated products being installed on the building.

We changed all the spandrel panels, ensuring they now had adequate cavity barriers and non-combustible insulation creating a barrier between the floors. Due to the planning constraints, there was no requirement or option to change the aesthetics of the building. The external facade was instead changed into a combination of Rockpanel and VitraDual, these were compliant products while achieving the same aesthetics and bringing the building in line with fire safety requirements.

Due to the changes in work scope sequencing and logistics, there was an ever-moving target however this was managed by working openly and honestly with our clients, keeping them up to date with the changes and inviting them to develop these solutions so that all stakeholders were in agreeance. We focused on heightened and enhanced communication on a weekly basis and bespoke lookaheads to achieve this.

Related case studies

We were invited to participate in this project at a very early preconstruction stage, this enabled us to work closely with the client’s design team to ensure the developing proposal suited the client’s requirements as well as met all standard compliance criteria. TSL’s industry known ability to work with minimal disruption was heavily leaned on […]

The client brief consisted of an entire facial uplift to the main entrance & external facade of the hotel, to be completed alongside the internal refurbishment of this wing of the building. An important part of this scheme was being involved with the clients design team from the start, this enabled us to work with […]

We completed this project during lockdown 1.0 and we thoroughly enjoyed what is typically a complicated project due to the curved nature of the existing substrate and subsequent panels. The curved nature of the building requires a pinpoint accurate design & procurement period to ensure the panels are created millimeter perfect to achieve the desired […]

Latest News

Antony Knight Project Manager

Employee Spotlight – Antony Knight

Antony celebrates his six-year anniversary this month so we felt there’s no better person to ask about what it’s like …

Read More >

Meon Milton on the Move

Great to see Meon Milton FC under 7’s in their new TSL kit, they’ve made a strong start and we …

Read More >

Employee Spotlight – Lily Sait

Lily celebrates her one year anniversary with TSL this month so we’ve taken some time to learn more about her …

Read More >