Waverley House, Bristol

Waverley House, Bristol

Client: Unite Intergrated Solutions

Background: After recent tragic events in London, the construction industry has taken a review of its materials installed, the existing cladding system was surveyed and was deemed to be non-compliant so was required to be replaced. The existing roof covering was notably coming to the end of its serviceable life and was sanctioned for replacement alongside the wall cladding.

Scope Of Service: Removal of existing non-compliant cladding system and replace with new A1 rated compliant system, support structure remedial works, structural concrete repair works with 10-year guarantee across the building, complete roof refurbishment including thermal upgrade to achieve a 20-year guarantee, with new lightening protection system installed and certified.

Form Of Contract: Purchasing Contract

Contract On Site: 10 Weeks

After the tragic events of Grenfell Tower, London; a review of cladding materials currently installed on buildings was initiated. Waverly House was found to have a non-compliant cladding panel installed and as a matter of urgency, TSL was mobilised almost immediately to remove the panels and temporarily cover the building with compliant finishes, until a more permanent solution could be proposed and agreed.

During the removal of the non-compliant cladding panels it was noted that the support structure was in need of re-fixing and replacement in limited areas, this was due to the concrete structure below becoming unstable in places. The concrete reinforcement bars had begun corroding in places causing larger parts of the concrete to fail and breakaway.

TSL had previously undertaken an asset condition survey for the clients property portfolio which demonstrated the conditions and life spans for the roofs on all of their properties. Waverly House’s roof was coming to the end of its serviceable life with it due to be replaced the following year, the decision was made by the client to undertake these works concurrently with the external façade works, leaving TSL to come up with solutions for a full envelope solution.

TSL’s proposals for a compliant ‘A1’ fire rated panel were accepted by local authority planning so the support structure remedial works began while the panels were manufactured. The failing and corroding concrete reinforcement was broken back, treated and recovered with new concrete sections with the whole facade coated in a liquid protection membrane the achieved a 10-year guarantee. The roofs were stripped back to existing substrate which was repaired where necessary and the new system was installed with the new thermal upgrade to meet current regulations.

TSL acted as the principal contractor throughout the works, with high communication to all relevant parties, including building control, structural engineers, client representatives and consultants just to name a few.

The regional manager (Mike Jenkins) for the client had this to say on TSL performance “We’ve worked with TSL on multiple smaller projects as we often use them for our emergency call-outs and love their commitment to service, however can’t applaud them enough for delivering the full envelope safely and on time with such a restricted programme!”

 

 

HLP_B_190111_3002
HLP_B_190111_3108

Related case studies

The client brief consisted of an entire facial uplift to the main entrance & external facade of the hotel, to be completed alongside the internal refurbishment of this wing of the building. An important part of this scheme was being involved with the clients design team from the start, this enabled us to work with […]

We were invited to participate in this project at a very early preconstruction stage, this enabled us to work closely with the client’s design team to ensure the developing proposal suited the client’s requirements as well as met all standard compliance criteria. TSL’s industry known ability to work with minimal disruption was heavily leaned on […]

We completed this project during lockdown 1.0 and we thoroughly enjoyed what is typically a complicated project due to the curved nature of the existing substrate and subsequent panels. The curved nature of the building requires a pinpoint accurate design & procurement period to ensure the panels are created millimeter perfect to achieve the desired […]

Latest News

Antony Knight Project Manager

Employee Spotlight – Antony Knight

Antony celebrates his six-year anniversary this month so we felt there’s no better person to ask about what it’s like …

Read More >

Meon Milton on the Move

Great to see Meon Milton FC under 7’s in their new TSL kit, they’ve made a strong start and we …

Read More >

Employee Spotlight – Lily Sait

Lily celebrates her one year anniversary with TSL this month so we’ve taken some time to learn more about her …

Read More >